Bennington Township:
Asphalt Paving:
*Waugh Road from Bennington Road to .32 miles south; 0.32 miles.
*Reconstruction project
includes tree removal, pulverizing, base repair, ditching, seeding, etc. to
prepare for 2011 re-paving.
Sealcoat Projects:
Grand River Road from
M-52 west to the township line; 2.98 miles.
Bennington Road from M-52 east to the township line; 3.02 miles.
Delaney Road from Brewer Road to Grand River Road; 1.00 miles.
Friegel Road from Bennington Road to Grand River Road; 3.44 miles.
Gravel Projects:
Delaney Road from Grand
River Road to .15 miles south; 0.15 miles.
Beardslee Road from Grand River Road north to the dead end; 0.31 miles.
Tree Removal:
Garrison Road from M-52 to Ruess Road; 1.01 miles.